The long-awaited Graham Road Construction Project in Stow and Cuyahoga Falls is set to begin on Monday March 31.

9 4 LINKEDINCOMMENTMORE

The long-awaited Graham Road Construction Project in Stow and Cuyahoga Falls is set to begin Monday (March 31).

Kenmore Construction Company says the first step will be a shift in traffic patterns on Graham Road from Bath Road through and including Wyoga Lake Road.

Construction work will begin on the north side of Graham Road in this area with saw cutting, roadway and curb removal, storm sewer installation, and drive approach installation.

Work on the north side is supposed to be completed in four to six weeks.

Traffic will be maintained to all businesses. Work on this phase will be completed by July 2014.

At the same time, utility companies will be working between Bath Road and the railroad tracks. Kenmore Construction will be completing the project in phases from the west to the east.

For additional information about the Graham Road Construction Project, please visit www.stow.oh.us for detailed plans and a map of the project area.